Project Updates
Below you will find the latest updates for projects in development and permitting. You can find more information about the different phases of development under Oil and Gas 101. If you have additional questions, please reach out to us on the Oxy Response Line. Operational timeframes are impacted by various factors and are subject to change; we will keep you updated via this web page.
Locations Under Development
Hickory ODGP
We have permit approval from both state and local agencies. Work is planned to begin in late 2024.
Sprout ODGP: Rademacher, Clover, and Alfalfa
We have permit approval from both state and local agencies.
Rademacher: We began drilling in late June and will finish drilling the first half of wells in August 2024.
Clover and Alfalfa: Work will begin on these wells in the Fall of 2024.
Important Links
Dec 2023 - Sprout Completeness Notice
Dec 2023 - Sprout Community Meeting Poster Slides
Nov 2023 - Community Meeting Invite
Nov 2023 - Community Meeting Invite (C)
Nov 2023 - Community Meeting Invite (A)
Jun 2023 - Weld County Permit Notice (A)
Oak ODGP: Alder and Acacia
We have permit approval from both state and local agencies. Pad construction on the Acacia location is scheduled to begin in the fall 2024.
Mt. Democrat ODGP
Berry Farms: Interim reclamation is expected to conclude in July 2024.
Swartz: Completions activities started in late June and work will complete in the early fall.
Camenisch: Horizontal drilling is underway. Completions is expected to begin in August.
Important Links
July 2024 - Completions Notice (C)
June 2024 - Air Monitoring Summary (S)
June 2024 - Air Monitoring Summary (C)
Apr 2024 - Air Monitoring Summary (S)
May 2024 - Swartz Completions Notice
Feb 2024 - Air Monitoring Summary (B)
Jan 2024 - Air Monitoring Summary (B)
Nov 2023 - Air Monitoring Summary (B)
Sept 2023 - Air Monitoring Summary (B)
Aug 2023 - Air Monitoring Summary (B)
July 2023 - Drilling & Pad Construction (C)
July 2023 - Air Monitoring Summary (B)
June 2023 - Air Monitoring Summary (B)
May 2023 - Air Monitoring Summary (B)
Apr 2023 - Air Monitoring Summary (B)
Mar 2023 - Air Monitoring Summary (B)
Mar 2023 - Drilling & Pad Construction (S)
Feb 2023 - Air Monitoring Summary (B)
Jan 2023 - Air Monitoring Summary (B)
Sept 2022 - Drilling & Pad Construction (B)
Jun 2022 - Completeness Notice
North Core ODGP
Blue Chip: All major operations have been completed. Periodic work will take place as reclamation continues. Please connect with a member of our Stakeholder Relations team if you have specific questions.
Rainbow: A smaller rig will be performing work through the third week in July and crews will not be back until the end of the year.
Important Links
June 2024 - Air Monitoring Summary (R)
Apr 2024 - Air Monitoring Summary (B)
Apr 2024 - Air Monitoring Summary (R)
Mar 2024 - Air Monitoring Summary (R)
Mar 2024 - Air Monitoring Summary (B)
Feb 2024 - Air Monitoring Summary (R)
Feb 2024 - Air Monitoring Summary (B)
Jan 2024 - Air Monitoring Summary (R)
Jan 2024 - Air Monitoring Summary (B)
Dec 2023 - Air Monitoring Summary (B)
Dec 2023 - Air Monitoring Summary (R)
Nov 2023 - Air Monitoring Summary (B)
Nov 2023 - Air Monitoring Summary (P)
Sept 2023 - Air Monitoring Summary (R)
Sept 2023 - Air Monitoring Summary (B)
Aug 2023 - Air Monitoring Summary (B)
Aug 2023 - Completions Notice (R)
July 2023 - Air Monitoring Summary (B)
July 2023 - Air Monitoring Summary (R)
Jun 2023 - Air Monitoring Summary (B)
Jun 2023 - Air Monitoring Summary (R)
May 2023 - Completions Notice (B)
May 2023 - Air Monitoring Summary (B)
May 2023 - Air Monitoring Summary (R)
Apr 2023 - Air Monitoring Summary (B)
Apr 2023 - Air Monitoring Summary (R)
Mar 2023 - Air Monitoring Summary (B)
Mar 2023 - Air Monitoring Summary (R)
Nov 2022 - Drilling & Pad Construction (R)
Nov 2022 - Drilling & Pad Construction (B)
Sept 2022 - Community Meeting Slides
Aug 2022 - Community Meeting Invitation (R)
Pikes Peak ODGP
Moser: Completions Activities are completed.
Wardell: Completions Activities are completed.
Hethcock: Completions Activities are expected to complete in July 2024.
Important Links
June 2024 - Air Monitoring Summary (W)
June 2024 - Air Monitoring Summary (M)
June 2024 - Air Monitoring Summary (H)
Apr 2024 - Air Monitoring Summary (H)
Apr 2024 - Air Monitoring Summary (M)
Apr 2024 - Air Monitoring Summary (W)
Mar 2024 - Air Monitoring Summary (M)
Feb 2024 - Air Monitoring Summary (W)
Feb 2024 - Air Monitoring Summary (M)
Jan 2024 - Air Monitoring Summary (W)
Jan 2024 - Air Monitoring Summary (M)
Dec 2023 - Air Monitoring Summary (H)
Dec 2023 - Air Monitoring Summary (W)
Nov 2023 - Air Monitoring Summary (W)
Nov 2023 - Air Monitoring Summary (H)
Sept 2023 - Air Monitoring Summary (W)
Aug 2023 - Air Monitoring Summary (M)
July 2023 - Air Monitoring Summary (M)
Jun 2023 - Air Monitoring Summary (M)
May 2023 - Drilling & Pad Construction (W)
Dec 2022 - Completeness Notice
Land Fed ODGP
Estimated interim reclamation began in June 2024.
Flower ODGP
Schmerge: Horizontal drilling is expected to begin in late July.
Vista: Completions activities began in July 2024 and are expected to wrap up in fall 2024.
Lizzy ODGP
The first portion of drilling has finished. Crews will continue to be onsite to wrap up completions activities for the first portion of the project and will begin drilling the second portion in August.
Salazar ODGP
Completions activities are expected to begin in fall 2024.
Important Links
Apr 2024 - Air Monitoring Summary
Oct 2023 - Drilling & Pad Construction Notice
Aug 2023 - Completeness Notice
Feb 2023 - Weld County Permit Notice
Labrisa ODGP
Completions activities began in June 2024 and will wrap up in August.
Fort Lupton ODGP: Griswold
Various construction work continues and is expected to continue intermittently through December 2024.
Locations in Planning and Permitting
Geothermal Pilot Project
Geothermal energy is a form of renewable energy derived from the heat stored beneath the earth's surface. We are planning on using our industry-leading expertise in drilling and carbon management to work towards Net Zero emissions goals. Oxy is working through the permitting process on a geothermal project in your community. The two-well project requires permits from both the Colorado Energy and Carbon Management Commission (ECMC) and Weld County. The timeline for development is based on obtaining the required permits and drilling rig availability. At this time, we estimate that drilling will start in 2025. We commit to keeping you updated throughout the permitting process and providing additional details before beginning construction.
Tulip ODGP
We are currently working through the permitting process. Please click the link to the right for project location and details.
Cypress ODGP
We continue to work through the state and local permitting processes. The Energy and Carbon Management Commission has determined the application to be complete.
Locations Previously Developed
Beierle and Lapka ODGPs
We will soon be conducting work at this existing oil and natural gas location. This temporary work involves using temporary water tanks and other industry equipment to pump water into the existing wells. These operations is currently scheduled to begin in early June 2024 and last two to three weeks. Please call the Response line for additional details about timing and operations near you.
Jodster ODGP
You may have received information about this area being evaluated for a proposed project. If you live nearby and would like to provide feedback, please feel free to contact a member of our stakeholder relations team.